Project Details

A challenging project which was awarded in November, 2010 and had to be completed no later than February 13, 2011. Sitting atop Lower Monumental Dam, Kuney Construction and its team lowered the necessary equipment down into the bottom of Monolith 15. From there, a section of the face was demolished and replaced. The contract was incredibly time sensitive. Kuney Construction completed all work by the February deadline, including replacing an optional section of the wall.

Project Specs

Location

Kahlotus, Washington

Owner

Army Corps of Engineers

Completion

2012

Size

< $10m